Ontario's Excess Soil Rules: Testing, Tracking and the Registry

1 January 2022  ·  Environmental  ·  6 min read

Ontario's On-Site and Excess Soil Management Regulation turned excavated soil from something a contractor hauled away into a regulated material with sampling, documentation and a public registry behind it.

How it was phased in

O. Reg. 406/19 was finalized in December 2019 and brought in over several years. Reuse rules, risk-based standards and waste designation provisions took effect on 1 January 2021. Testing, tracking and registry requirements followed on 1 January 2022, with the Excess Soil Registry going live shortly before. The Province paused parts of the second phase in April 2022, moving certain requirements to 1 January 2023. Restrictions on depositing excess soil at landfilling sites formed the final phase, and the date for that prohibition has since moved again.

What it means on a project

For any project generating enough excess soil to be caught by the regulation, the work is front-loaded. Before soil moves, a qualified person oversees an assessment of past uses, a sampling and analysis plan, a soil characterization report and a destination assessment. Notices are filed in the registry. The soil then has to reach the destination that was declared.

This is why excess soil has become a schedule item rather than a line in a haulage quote. Engaging the qualified person late is the most common way projects lose weeks.

Where it connects to environmental site assessment

Soil characterization and a Phase 1 or Phase 2 ESA answer related but distinct questions. A Phase 2 asks whether contamination is present on the site; excess soil work asks whether the material being removed can lawfully go where it is proposed to go. On a redevelopment carrying both, sequencing them together saves duplicated drilling and laboratory cost.

Practical advice

  • Identify early whether the volume and location bring the project within the regulation.
  • Bring the qualified person in during design, not after excavation starts.
  • Where a Phase 2 ESA is also required, plan the two investigations as one field programme.
  • Confirm the current position on landfill deposit restrictions — this part has been amended more than once.

Moving soil off a site?

We can advise on the assessment and documentation the excess soil regulation requires, alongside any ESA work.

Request a Quote
About this article Written by Ben Engineering, which prepares reserve fund studies, depreciation reports, property condition assessments and environmental site assessments in Ontario and British Columbia. This is general information about regulatory and standards changes, not advice for a specific property. Requirements change — confirm the current position before acting.