Ontario's On-Site and Excess Soil Management Regulation turned excavated soil from something a contractor hauled away into a regulated material with sampling, documentation and a public registry behind it.
How it was phased in
O. Reg. 406/19 was finalized in December 2019 and brought in over several years. Reuse rules, risk-based standards and waste designation provisions took effect on 1 January 2021. Testing, tracking and registry requirements followed on 1 January 2022, with the Excess Soil Registry going live shortly before. The Province paused parts of the second phase in April 2022, moving certain requirements to 1 January 2023. Restrictions on depositing excess soil at landfilling sites formed the final phase, and the date for that prohibition has since moved again.
What it means on a project
For any project generating enough excess soil to be caught by the regulation, the work is front-loaded. Before soil moves, a qualified person oversees an assessment of past uses, a sampling and analysis plan, a soil characterization report and a destination assessment. Notices are filed in the registry. The soil then has to reach the destination that was declared.
This is why excess soil has become a schedule item rather than a line in a haulage quote. Engaging the qualified person late is the most common way projects lose weeks.
Where it connects to environmental site assessment
Soil characterization and a Phase 1 or Phase 2 ESA answer related but distinct questions. A Phase 2 asks whether contamination is present on the site; excess soil work asks whether the material being removed can lawfully go where it is proposed to go. On a redevelopment carrying both, sequencing them together saves duplicated drilling and laboratory cost.
Practical advice
- Identify early whether the volume and location bring the project within the regulation.
- Bring the qualified person in during design, not after excavation starts.
- Where a Phase 2 ESA is also required, plan the two investigations as one field programme.
- Confirm the current position on landfill deposit restrictions — this part has been amended more than once.
Related
Phase 2 Environmental Site Assessment · Site Remediation · CSA Z769-00 Reaffirmed in 2023 — The Phase 2 ESA Sta… · July 2011: The Overhaul That Shaped Ontario Site Ass… · All Insights articles
Moving soil off a site?
We can advise on the assessment and documentation the excess soil regulation requires, alongside any ESA work.
Request a Quote